Case study narrative
Project narrative
Current 7NT personnel have been involved on the Deep Rock Tunnel Connect project since 2007. 7NT drill crews, engineers, and laboratory personnel have been responsible for performing the geotechnical subsurface investigation and laboratory services, including soil and rock, for the Design Phase of this project. 7NT construction inspectors have continued to provide inspection services into the construction phase.
The first portion of the geotechnical investigation program required the drilling of five vertical borings to obtain soil samples for geological exploration and geotechnical analyses, water pressure testing in rock for five borings, and installation of five piezometers in the area of the proposed tunnel. This information was utilized by the City and its design engineer to aid in selection of the proper alignment of the tunnel.
The five borings were each drilled to approximately 280 feet in depth. Approximately 100 feet of drilling was in soil overburden and approximately 180 feet in bedrock. Water pressure testing via wireline packer testing was performed on all five rock core borings. Five piezometers were also installed as part of the fieldwork to a depth of approximately 230 feet each.
The field work was performed during January to March 2009 under very adverse winter weather conditions. Despite weather-related challenges, the work was completed on time and in budget.
Drilling work for the second portion of the geotechnical investigation included drilling along the tunnel alignment in addition to shaft, drop structure, and pump station locations. Portion 2 included 63 borings ranging from 15 feet to 305 feet in depth with overburden ranging from 50 feet to 115 feet. Overburden drilling predominantly dealt with heaving sands while performing standard penetration testing, split spoon sampling, and Shelby tube sampling. Thirty-eight piezometers were installed totaling approximately 4,000 feet. Approximately 250 hours of packer testing was performed, and nine borings were performed at a 20 degree incline.
Several areas along the tunnel alignment had suspected HTRW contamination. Geo-environmental investigation including drilling, well installation, soil and groundwater sampling, and chemical laboratory analysis were performed. Appropriate personnel protection equipment was used, and hazardous waste was contained in drums for safe and proper disposal.
Environmental and continuous sampling was performed in several borings. Each piezometer was set with a flush mounted cover and a concrete pad stamped for identification. A total of approximately 6,500 feet of HQ-size rock was cored during the project, and the quality of rock cores obtained required minimal preparation by the laboratories to perform designated testing. A total of approximately 4,500 feet of overburden was drilled or sampled.
Scope of work
Technical scope
Subsurface exploration scope
- Developing a site-specific safety plan
- Performance of exploratory borings
- Monitoring air at each boring collar
- Sampling soil
- Performing water pressure testing
- Protecting and preserving soil and rock core samples
- Screening samples using Photo Ionization Detector
- Collecting soil samples for chemical and environmental testing and analyzing for sulfates, chlorides, volatile and semi-volatile organic compounds
- Installing piezometers
- Backfilling borings
Laboratory testing
- Moisture content
- Hydrometer analysis
- Consolidation analysis of soil
- Unconfined compression of rock
- Rock moduli in uniaxial compression
- Rock core bulk density
- Extruded thin walled tube sample
- Chemical analysis of soil
- Atterberg limits
- Grain size analysis
- Punch-penetration and slake durability
- Cerchar abrasivity index
- Direct shear strength
- Splitting tensile strength of rock
Field experience relevant to this contract
- On shore, off shore, river line soil drilling and sampling
- Rock drilling and coring
- Geo environmental investigations
- In-situ borehole testing
- Well installation
- Instrumentation installation
- Laboratory testing (geotechnical and environmental)
- Rock joint mapping
- Survey of borehole locations
Engineering experience relevant to this contract
- Geotechnical design, modeling, analysis, reporting
- Construction quality assurance (QA) testing
- Site exploration reports
- Engineering reports